Project Information: Lidl HeadQuarter Offices in Tallaght Dublin 24.

Lidl’s new HQ and medical centre, Tallaght in Dublin 24 is due to complete by December 2015.

The site is located within high density retail and commercial and residential area of Tallaght. There is also an active Lidl store located adjacent to the site

This project involves the building of five blocks ranging in height from two storeys to four storeys, the Tallaght project’s floor area will extend to 20,958sqm. One of the blocks extending to 5,192sqm will accommodate a two-storey supermarket.

As this project ran to a tight schedule Flood Super Wideslab® and Precast Stairs was able to provided an efficient precast concrete floor slabs solution.

Some of the advantages why our customer decide that Super Wideslab® was there best option on this development.

  • Faster installation – twice as fast as Hollowcore to install.
  • Cast in lifting system – fully anchored cast-in lifters are designed so that the units can be lifted from the trailer into final position without the need for cradles, chains or bearing into position.

Solutions and Recommendations:  Flood Super Wideslab® Precast Concrete Floors and Precast Stairs

Project Team:

Contractor:  John Sisk & Sons Ltd,

Architect:    MCA Architect

Quantity Surveyor: Kerrigan Sheanon Newman

Engineer: Barrett Mahony Consulting Engineers Ltd

Sq. Metres:   1,733 Sq. Meters