Flood Precast provided 200mm Hollowcore Slabs and Precast Stairs to the main contractor Morgan Sindall at Methytr Bus Station in South Wales.
Merthyr Tydfil’s new multimillion-pound town centre bus station was completed in October 2020 on the site of a former police station site on Swan Street in the town. The new bus station will be located closer to the town’s railway station with the aim of creating a new transport interchange facility and link-up with rail’s South Wales Metro and to allow new development opportunities to be considered for the current bus station site.
The project has been co-designed with the Cardiff Capital Regional Transport Authority and the council has retained Capita to support the management of the construction contract.
Project: Merthyr Tydfil Bus Station
Principal Contractor Morgan Sindall Construction
Project Period 15/07/2019 – 20/10/2020
Engineer: CAPITA
For more information on our range of concrete products contact our team at info@floodprecast.co.uk
Products: Precast Concrete Stairs and 200mm Hollowcore flooring slabs